Baugenehmigung zur Errichtung einer Anlage beantragen
Inhalt
Begriffe im Kontext
Fachlich freigegeben am
Fachlich freigegeben durch
- § Section 71 Building Regulations of the State of Saxony-Anhalt (BauO LSA)
- § Section 63 Building Regulations of the State of Saxony-Anhalt (BauO LSA)
- Building Submission Ordinance (BauVorlVO)
- Building Code (BauGB)
- Ordinance on the structural use of land Land Use Ordinance (BauNVO)
- Act on Energy Conservation and the Use of Renewable Energies for Heating and Cooling in Buildings (Building Energy Act (GEG))
- Annex for the administrative regulation on the introduction of technical building regulations
If you want to build an installation that requires approval, you will need a building permit. You must submit a building application for this.
Before you can erect an installation that requires approval, you need a building permit.
To do this, you submit a building application to the responsible lower building supervisory authority. Depending on the project, you may need the support of an authorized draftsman (e.g. civil engineer or architect).
- Building application (via online service or form)
- Extract from the official real estate register
- Site plan
- Construction drawings
- Building description
If applicable:
- Proof of stability
- Fire protection certificate
- Information on the secured development
Please contact your local building supervisory authority to find out which documents you need to submit for your specific building project.
- Complete building application
- Building project complies with public law regulations
- If not, you can apply for deviations with the building application
The costs depend on the following factors:
- The time and effort involved in checking your building application
- Expected costs of the construction work
at least € 50
Fees for a building permit for every €500 or part thereof of the chargeable construction value = €5
You can apply for a building permit for the construction of an installation electronically via the online service or in paper form using the form.
Proceed as follows when using the form:
- Complete the form.
- Add the required building documents.
- Submit the application documents to the responsible lower building supervisory authority.
- If necessary, the lower building supervisory authority will ask you to make an advance fee payment.
- Make the advance payment.
- If documents are missing or there are other ambiguities, you will be asked to resolve these ambiguities.
- In this case, submit the missing or amended documents or the clarification.
- The lower building supervisory authority will check your application and involve the municipality and the necessary authorities.
- You will then receive the building permit and a notification of fees.
- Pay the fees.
The building supervisory authority will decide on your building application within 3 months. The deadline begins with the confirmed date of receipt.
Exception: The authority can extend the deadline by a maximum of 2 months if there is an important reason. If the deadline is extended, you will be informed by the responsible lower building supervisory authority, stating the reasons and the expected date of the decision.
If you have a building permit, you must submit a notice of commencement of construction to the lower building supervisory authority at least one week before the start of construction.
- Construction of facilities Permit
- Applying for planning permission for the construction of a facility
- Required for the construction of all non-procedure-free and non-permit-free structures
- Application via online service or publicly published forms required
- Depending on the project, an authorized designer may be required
- Responsible: lower building supervisory authority
The lower building supervisory authority is responsible.