Errichtung und Betrieb einer überwachungsbedürftigen Anlage nach Betriebssicherheitsverordnung Erlaubnis von Füllstellen
Inhalt
<div lang="en-x-mtfrom-de">Construction and operation of a system requiring monitoring in accordance with the Industrial Safety Ordinance Permitting filling points</div>
<div lang="en-x-mtfrom-de">Ensuring operational safety - apply for permission to set up and operate filling stations</div>
Begriffe im Kontext
<div lang="en-x-mtfrom-de">Permission to fill point</div> (Synonym)
Fachlich freigegeben am
03.11.2023
Fachlich freigegeben durch
nicht vorhanden
If you have a filling point for flammable liquids with a flash point <23°C and a handling capacity >1. If you want to build, operate or make certain changes to the facility that affect the safety of the system, you must apply for a permit.
Filling points are systems that are permanently installed or used permanently at the same location and have a handling capacity of more than 1000 liters per hour. At filling points, transport containers are filled with flammable liquids with a flash point <23°C. This is a facility that requires monitoring.
You need permission from the relevant authority if you:
You need permission from the relevant authority if you:
- would like to build and operate a filling station
- want to make changes to the design or operating method that affect the safety of the system
- limited
- limited
- under conditions
- with conditions
Informal application with the following information:
- Last name, first name, company name
- Applicant's address
- Contact information (email, telephone, fax)
- Information about what type of permission is desired
- Construction and operation
- Change and operation or
- Partial permission
- Indication of the operating location
- Subject of the application
- Description of the facility
- Description of the system technology and interaction with other systems
- Piping and instrument flow diagram (P&ID flow diagram)
- Safety data sheets
- Description of operation
- Overview plan
- Site plan
- Floor plan/technical plan
- Ex zone plan
- Explosion protection concept
- Fire protection information
- Description of the liquid-tight area
- Calculation of manufacturing costs
- Other facilities
- Test report from an approved monitoring body (ZÜS). The test report must confirm that the system can be operated safely if the measures mentioned are adhered to.
- The system for which you are applying for permission must be a system that requires permission.
- You must build and operate filling stations using state-of-the-art technology.
- Your documents must be complete, plausible and meaningful.
- The test report from the approved monitoring body (ZÜS) must confirm that the system applied for can be operated safely if the measures specified in the documents, including the tests, are adhered to.
Fees are charged for processing the permit application in accordance with the fee schedule for the areas of occupational safety and plant and product safety (ArbSchGebO HA).
The amount of the fee depends on the time required to review the application documents and prepare the permit
The amount of the fee depends on the time required to review the application documents and prepare the permit
- Submit the application for approval of the system requiring monitoring with the necessary documents, including the test report from the approved monitoring body (ZÜS), to the responsible authority.
- If there is a requirement for approval under the Federal Immission Control Act, you will receive the application documents back, as a permit under the Industrial Safety Ordinance will then be checked as part of the necessary approval under the Federal Immission Control Act.
- The responsible authority will make its decision after review and communicate it to you.
The competent authority must decide on the application within three months of receiving it.
The permission expires if:
- You have not started construction of the facility within two years of the permit being granted
- You have interrupted the construction of the system for two years or longer
- You have not operated the system for a period of three years
Contradiction:
- You can object to the decision within one month of the announcement.
- You must submit the objection to the responsible authority in writing or for recording.
- Ensuring operational safety - apply for permission to set up and operate filling stations
- Construction and operation of a system requiring monitoring in accordance with the Industrial Safety Ordinance Permitting filling points
- A filling point is a facility that is permanently installed or used at the same location and has a handling capacity of flammable liquids (flash point < 23°C) of more than 1000 liters per hour
- They are “systems requiring monitoring” that must be assembled, installed and operated according to the state of the art.
- Anyone who wants to build or operate such a filling station or make changes to its design and operation requires a permit.
- Permission can be granted:
- under conditions
- limited
- limited
- be subject to conditions
- You can submit the application informally in writing or electronically.
- An application for partial permission is possible.
- The Office for Consumer Protection is responsible.