Beseitigung von Anlagen
Inhalt
Begriffe im Kontext
<div lang="en-x-mtfrom-de">Termination request</div> (Synonym), <div lang="en-x-mtfrom-de">Cancellation request - already applied for</div> (Synonym), <div lang="en-x-mtfrom-de">Demolitions of buildings - already requested</div> (Synonym), <div lang="en-x-mtfrom-de">Demolition permit - already applied for</div> (Synonym), <div lang="en-x-mtfrom-de">Demolition permit - already applied for</div> (Synonym), <div lang="en-x-mtfrom-de">Construction matters</div> (Synonym)
Fachlich freigegeben am
08.03.2024
Fachlich freigegeben durch
nicht vorhanden
§ 59 Hamburg Building Code (HBauO)
www.landesrecht-hamburg.de/bsha/document/jlr-BauOHA2005V11P59
§ 61 Hamburg Building Code (HBauO)
www.landesrecht-hamburg.de/bsha/document/jlr-BauOHA2005V11P61/part/S
§ 62 Hamburg Building Code (HBauO)
www.landesrecht-hamburg.de/bsha/document/jlr-BauOHA2005V11P62/part/S
www.landesrecht-hamburg.de/bsha/document/jlr-BauOHA2005V11P59
§ 61 Hamburg Building Code (HBauO)
www.landesrecht-hamburg.de/bsha/document/jlr-BauOHA2005V11P61/part/S
§ 62 Hamburg Building Code (HBauO)
www.landesrecht-hamburg.de/bsha/document/jlr-BauOHA2005V11P62/part/S
If you want to remove a building, you usually need a demolition permit. You must apply for the demolition permit from the responsible authority. You must have the demolition permit before you start the demolition work.
The specific documents depend on the individual case. Depending on the type and scope of your application, different documents will be required from you. Your person authorized to submit building plans can inform you accordingly. You will also be informed accordingly when you apply via the online service.
- They intend to remove a building structure.
- You have a person with building permit authorization at your side. This could be an architect or a civil engineer, for example.
- You or your person authorized to submit building plans submit an application for approval to the responsible authority.
- The responsible authority will examine your application and, if necessary, request any necessary documents or information from you.
- You will receive a written approval or rejection notice.
- You will receive a fee notice and pay the fees
The processing time depends on the scope of the project applied for and can take 1 to 3 months after the required documents have been submitted in full.
You may also need permission or approval from another authority (e.g. the monument protection authority).
- Apply for demolition permit
- Anyone who wants to remove a building requires a demolition permit
- Demolition permit must be applied for
- Demolition permit must be obtained before demolition work begins
If you want to find out exactly who is responsible for your request, please follow the link to Authority finder Hamburg