Genehmigung der Aufnahme des Betriebs eines Energieversorgungsnetzes nach dem Energiewirtschaftsgesetz
Inhalt
Begriffe im Kontext
- Eintragung, Änderung der Rechtsform oder Schließung eines Unternehmens (Registrierungsverfahren und Rechtsformen für geschäftliche Tätigkeiten)
Fachlich freigegeben am
Fachlich freigegeben durch
The commencement of operation of an energy supply network requires a permit in accordance with the Energy Industry Act by the competent authority under state law.
The commencement of operation of an energy supply network requires a permit in accordance with Section 4 (1) of the Energy Industry Act (EnWG) by the competent authority under state law.
By applying for the commencement of operation of the energy supply network, the applicant must demonstrate that he has the personnel, technical and economic capacity and reliability to ensure long-term network operation in accordance with the provisions of the EnWG.
By applying for the commencement of operation of the energy supply network, the applicant must demonstrate that he has the personnel, technical and economic capacity and reliability to ensure long-term network operation in accordance with the provisions of the EnWG.
The amount of the fees is determined - according to Annex 1 to § 1 paragraph 1 of the General Fee Schedule of the State of Lower Saxony No. 27.1.1. - depending on the time spent.
However, a minimum of EUR 500.00 and a maximum of EUR 5,000 will be charged.
The competent authority shall take a decision within 6 months of the submission of complete application documents.
Authorisation for the operation of the network must be obtained prior to commencement. Section 4 (1) sentence 2 EnWG provides for a decision by the competent authority within 6 months of the submission of complete application documents. Accordingly, the application must be submitted in good time.
The commencement of operation of an energy supply network requires a permit in accordance with the Energy Industry Act by the competent authority under state law.
The responsibility lies with the Lower Saxony Ministry for the Environment, Energy, Building and Climate Protection.
This procedure can also be handled by a "Point of Single Contact". The "Point of Single Contact" is a special service offered by the municipalities and the state for service providers.