Genehmigung für wesentliche Änderung einer genehmigungsbedürftigen Anlage beantragen
Inhalt
Begriffe im Kontext
- Erlangung von Lizenzen, Genehmigungen oder Zulassungen im Hinblick auf die Gründung und Führung eines Unternehmens
Fachlich freigegeben am
Fachlich freigegeben durch
If you intend to make significant changes to an installation that requires a permit, you must apply for a permit from the responsible authority.
Do you operate an installation that requires a permit under immission control law, for which you already have a permit under immission control law, and are you planning to make significant changes to this installation? Significant changes exist if the change to the location, nature or operation could have adverse effects. If these are also significant for the approval requirements for installations requiring approval, approval is required.
A permit is also always required if the modification or expansion of the operation of installations requiring a permit causes the performance limits or the size of the installation to be reached. For this reason, significant changes to installations requiring approval must be reviewed by the immission control authority.
To do this, you must submit an application for a modification permit and submit all the necessary documents for the assessment. The application can be made in writing or electronically.
However, approval is not required if
- the adverse effects caused by the change are obviously minor and
- the fulfillment of the requirements of the approval requirements of the
Federal Immission Control Act for installations requiring approval is ensured.
This also applies if an approved installation or parts of an approved installation are to be replaced within the scope of the approval granted.
If the operator is of the opinion that the planned change is not significant, notification of the change to the competent authority is required.
- Modification of a plant subject to approval in accordance with the BImSchG Approval for significant modification
- A significant change exists in particular
- if the change
- the location
- the nature or
- operation of the installation requiring a permit may have adverse effects and
- these may be significant for the licensing requirements of installations requiring approval in accordance with the Federal Immission Control Act.
- Approval is always required if the modification or extension of the operation of the installation requiring approval results in performance limits or installation sizes being reached.
- Application: Electronic application under immission control law (EliA) or in writing
- Responsible: immission control authority
Please contact the immission control licensing authorities in Thuringia: Thuringian State Office for the Environment, Mining and Nature Conservation (TLUBN) or the districts and independent cities.
The responsible authorities are the immission control licensing authorities of the state of Thuringia in the form of the Thuringian State Office for the Environment, Mining and Nature Conservation (TLUBN) and the lower immission control authorities of the districts and independent cities.