Dies ist die interne Entwicklungsumgebung des FIM Portals. Bitte nutzen Sie die produktive Umgebung.

Immissionsschutz - Teilgenehmigung zur Errichtung und den Betrieb einer Anlage nach BImSchG beantragen

Baden-Württemberg 99063012001000 Typ 2

Inhalt

Leistungsschlüssel

99063012001000

Leistungsbezeichnung

Immission control - Apply for partial authorisation for the construction and operation of a plant in accordance with BImSchG

Leistungsbezeichnung II

Immission control - Apply for partial authorisation for the construction and operation of a plant in accordance with BImSchG

Leistungstypisierung

Typ 2

Begriffe im Kontext

nicht vorhanden

Leistungstyp

nicht vorhanden

SDG Informationsbereiche

nicht vorhanden

Lagen Portalverbund

nicht vorhanden

Einheitlicher Ansprechpartner

nicht vorhanden

Fachlich freigegeben am

nicht vorhanden

Fachlich freigegeben durch

nicht vorhanden

Teaser

The construction and operation of an installation listed in Annex 1 of the Fourth Ordinance on the Implementation of the Federal Immission Control Act (Ordinance on Installations Requiring Authorisation - 4th BImSchV) requires an immission control permit from the competent authority.

Volltext

The construction and operation of an installation listed in Annex 1 of the Fourth Ordinance on the Implementation of the Federal Immission Control Act (Ordinance on Installations Requiring Authorisation - 4th BImSchV) requires an immission control permit from the competent authority.

On application, it is also possible to issue such a licence in stages. With a partial licence, you can begin with the construction and operation of the approved project section. In individual cases, a partial permit can help to speed up the realisation of a project.

Erforderliche Unterlagen

The application must be accompanied by the documents required for an assessment. These are, for example

The competent authority may request further documents if necessary. Coordinate in advance with the responsible immission control authority or the specialised authorities involved in the procedure regarding the documents required for an assessment.

If official decisions concerning the installation are communicated as part of the authorisation procedure (e.g. building permit), the documents required for this must also be submitted.

Voraussetzungen

A partial licence may only be granted if there is a legitimate interest and the licensing requirements for the part of the installation comprising the partial licence are met. In addition, it must be possible to confirm in a preliminary forecast that the overall project is capable of being authorised. Individual issues may not be excluded from this process.

Kosten

The fees are based on the investment costs for the system.

Verfahrensablauf

The authorisation procedure requires a written application, which must be accompanied by the drawings, explanations and other documents required to check the authorisation requirements. If further documents are required by the responsible immission control authority or the respective specialised authorities for an assessment, these must be submitted subsequently. The procedure for a partial permit corresponds to that of a formal or simplified permit procedure for the construction and operation of an installation requiring a permit under immission control legislation. The parts of the entire installation not covered by the partial licence must be approved by further partial licences.

Bearbeitungsdauer

As a rule, the licensing authority must check whether the documents are complete within one month of receiving the application. If the application documents are not sufficient for an assessment, they must be completed by the applicant.

Once the application documents are complete, the statutory deadlines begin for the authorisation procedure under immission control law, which is seven months for new installations in a formal procedure and three months in a simplified procedure. The deadlines can be extended by three months if this is necessary due to the difficulty of the examination or for reasons attributable to the applicant.

Frist

Construction and operation of the system may only begin after the licence has been granted.

Weiterführende Informationen

nicht vorhanden

Rechtsbehelf

If the responsible immission control authority refuses to authorise the project, an appeal can be lodged against this or, in the case of decisions by the regional councils, an action can be brought.

Kurztext

nicht vorhanden

Ansprechpunkt

nicht vorhanden

Zuständige Stelle

nicht vorhanden

Formulare

nicht vorhanden