Verlegung oder Änderung von Telekommunikationslinien
Inhalt
Begriffe im Kontext
Fachlich freigegeben am
Fachlich freigegeben durch
If you are the owner or operator of a telecommunications line or a telecommunications network serving public purposes, you require the consent of the landowner for the relocation or modification of this infrastructure. If the property is a public traffic route, you must submit the application to the road owner. With this approval, you can obtain any other necessary permits. Once you have obtained all the necessary permits, you can generally start the construction work. Please note any conditions, ancillary provisions and agreed deadlines.
- Application in written or electronic form
- The application must contain information on the location of the relocation or modification of telecommunications lines, in particular which road and road components are affected, stating the network node and mileage
- The application must contain information on the type and depth of installation
- The application must be accompanied by a route plan, usually at a scale of 1:1000
The applicant must be the owner or operator of a public telecommunications network or a telecommunications line serving public purposes. The structural implementation for the laying or modification of the telecommunications line takes place in a public road.
As the owner or operator of public telecommunications networks or telecommunications lines serving public purposes, you apply for approval to lay cables in the public road, submitting complete application documents. The public highway authority examines the application and, if necessary, grants approval subject to conditions and instructions by means of a decision in accordance with the Telecommunications Act (TKG).
Under certain circumstances, an on-site meeting is required before the decision is issued.
Under certain circumstances, fictitious approval may also apply, i.e. approval is deemed to have been granted after a period of 3 months. The applicant is obliged to bear the administrative costs.
If application documents are subsequently submitted or amended, the deadlines for processing by the infrastructure manager and, in particular, the deadlines for fictitious approval begin anew.
- Laying or modification of telecommunications lines
- OZG service broadband expansion
- Laying and modification of telecommunications lines, approval in accordance with § 127 TKG
- Application for telecommunications companies
- for changes and relocations of telecommunications lines in traffic routes
- The property concerned is a public thoroughfare
- in writing or online
- Approval by municipality, district, independent city, state or federal government